Project Description
Gray’s AFA Lift Shafts
Client: Octavius
Approximate value: £1.5m
Start Date & Duration: Nov 2023 – Nov 2024- 12 months.
Description of the works (Scope):
Installation of 2 lift shafts over 2 platforms and link into an existing underpass.
Difficulties to overcome:
- Working on a live railway and within a busy station environment
- Design issues and delayed AFC issue
- Working with existing old structures
Positive / Notable Actions:
Working alongside client and designers to bring status to AFC.
Local Labour Percentage:
80%
Environmental Initiatives:
Waste Percentage Diverted From Landfill:
98.5%